Phase 'A' involves the utilisation of the existing 300 metre quay with a water depth of 14.5 metres and a total area of 130,000 square metres offering 1,488 container ground slots.
Phase 'B' entails the use of another 450 metre quay and an additional total area of 160,000 square metres offering 2,438 container grounds slots. This phase will also include the installation of 192 reefer points.
The final stage of the project involves the development
of an integrated intermodal facility.
| See an animation of the different phases of the Development ! |
|
|
|
|
|
| Quay Lenght |
300m
|
450m
|
750m
|
| Ground Slots |
1,488
|
2,438
|
3,926
|
| Reefer Points |
-
|
192
|
192
|
| Total Area |
130,000 sq.m
|
160,000 sq.m
|
290,000 sq.m
|
|
|
|